Abbey Court School

Strood, ME2 3SP

Client

Medway Council

Main Contractor

Architect

IID Architects

Project details

Abbey Court School is a special needs school catering to students with profound learning disabilities, which is maintained by Medway Council Local Authority. Our team at Edge Structures was privileged to serve as the lead structural and civil engineering consultants for the crucial ‘Phase 2’ expansion.

The ‘Phase 2’ development presented a state-of-the-art, two-story structure, consisting of: a grand, double-height assembly hall; a hydrotherapy pool; 14 specialised classrooms with medical hoists; an easily-accessible terrace; a library; and life skills facilities.

To enhance the integrity of the underlying 2.5m of Made Ground, vibro-compaction ground improvement was implemented throughout the building’s footprint. This strategic decision allowed us to forego the need for extensive piled foundations and a substantial suspended slab. This significantly reduced the cement usage and thereby minimised both the embodied carbon and the construction costs. A thorough embodied carbon assessment conducted by our team affirmed a substantial reduction of over 200tCO2e thanks to the ground improvement process.

The project’s primary superstructure exhibits a lightweight CLT construction.

In the end, our design achieved an embodied carbon footprint of 115kgCO2e/m2, comfortably surpassing the targets set forth by RIBA, SCORS, and LETI for the year 2030.

Emissions saved with the vibro scheme, compared to a scheme with piled foundations:

115kg C02e/m²

Embodied Carbon Achieved with the vibro scheme

536

one-way flights from London to New York

268

peoples consumption of meat, dairy and beer for 1 year

147

average family cars running for 1 year